EGL1 Update – Path open with Banksman during hours of 7am to 7pm
Continue readingPath Banksman – A1 north side near Skateraw
Vehicle signage
The Community Traffic and Travel Forum’s proposal for energy projects for construction vehicle signage has now been adopted for all…Continue readingVehicle signage
Over the past few months I’ve been experimenting with ways to make the East Lothian Field Names project easier to…Continue readingAutomating Field Name Progress Tracking
Hall Build – Week 25
There’s been a few delays recently around sequencing the connection of the borehole pipework into the outbuilding and laying the…Continue readingHall Build – Week 25
Check out our quarterly partnership newsletter via button, hard copies available on request from beth@elep.scotContinue readingEnergy Projects partnership Newsletter
East Lammermuir Warm Homes Project
With fuel prices rising, many East Lammermuir residents have already shown their interest in improving energy efficiency and moving away…Continue readingEast Lammermuir Warm Homes Project
The East Lammermuir Warmer Homes Project has now been launched to follow on from the early work and Feasibility Study…Continue readingEast Lammermuir Warmer Homes Project
Branxton Substation enabling works
To complete the new A1 slip road the temporary traffic barrier must be removed to tie in the new road.…Continue readingBranxton Substation enabling works
June 2026 A new DDHS exhibition will open on 26th June 2026. Below are some panels from the exhibition. Initial…Continue readingDDHS Exhibition: What does it mean?…Place-names in and around Dunbar.
Local traffic updates
Four roads updates for June including filming in Stenton, and nighttime works on the A1
Continue readingLocal traffic updates