It’s flower show week! Of course, that hasn’t stopped progress with the build, but TRF have made some extra efforts…Continue readingHall Build – Week 34
Category: New Village Hall
New Village Hall
Hall Build – Week 32
After a slight pause in posting (but not in building!), we have internal walls and ceiling going up! All the…Continue readingHall Build – Week 32
Hall Build – Week 29
Work continues, despite the heat! We’ve had a minor obstacle to overcome this week. An issue was discovered with one…Continue readingHall Build – Week 29
Hall Build – Week 28
Work continues on the walls… At the end of this week, we’ve got the east and west wings of the…Continue readingHall Build – Week 28
Hall Build – Week 27
We’ve got walls! Ok, not all the walls just yet, but the first solid sides to the main hall are…Continue readingHall Build – Week 27
Hall Build – Week 26
Concrete week! The Big Concrete Pour went ahead as scheduled on Wednesday this week. A slightly dodgy weather forecast turned…Continue readingHall Build – Week 26
Hall Build – Week 25
There’s been a few delays recently around sequencing the connection of the borehole pipework into the outbuilding and laying the…Continue readingHall Build – Week 25
Hall Build – Week 23
Lots of sand this week! A large stack of white and orange ton bags are gradually being diminished and the…Continue readingHall Build – Week 23
Hall Build – Week 22
It’s been a week of heavy digging by hand and by machine for the guys at TRF. The end result…Continue readingHall Build – Week 22
Hall Build – Week 21
The day(s) of the big drill finally arrived! From first thing on Monday, GreenHeat Renewables were on site in force…Continue readingHall Build – Week 21