Digger and dumper back on site this week. Not the great big ones we had at the start to do…Continue readingHall Build – Week 37
Category: New Village Hall
New Village Hall
Hall Build – Week 36
It’s raining… better get the roof up. All work this week has been “upstairs” (up scaffold) getting outer walls and…Continue readingHall Build – Week 36
Hall Build – Week 35
Busy week for the TRF guys, working on two sections at once. The stone masons have started work rebuilding and…Continue readingHall Build – Week 35
Hall Build – Week 34
It’s flower show week! Of course, that hasn’t stopped progress with the build, but TRF have made some extra efforts…Continue readingHall Build – Week 34
Hall Build – Week 32
After a slight pause in posting (but not in building!), we have internal walls and ceiling going up! All the…Continue readingHall Build – Week 32
Hall Build – Week 29
Work continues, despite the heat! We’ve had a minor obstacle to overcome this week. An issue was discovered with one…Continue readingHall Build – Week 29
Hall Build – Week 28
Work continues on the walls… At the end of this week, we’ve got the east and west wings of the…Continue readingHall Build – Week 28
Hall Build – Week 27
We’ve got walls! Ok, not all the walls just yet, but the first solid sides to the main hall are…Continue readingHall Build – Week 27
Hall Build – Week 26
Concrete week! The Big Concrete Pour went ahead as scheduled on Wednesday this week. A slightly dodgy weather forecast turned…Continue readingHall Build – Week 26
Hall Build – Week 25
There’s been a few delays recently around sequencing the connection of the borehole pipework into the outbuilding and laying the…Continue readingHall Build – Week 25