Highlights: Land purchase for the hall is moving to final stages, with all terms now agreed. Tender documents for the…Continue readingCommittee meeting, June 3rd 2025
Category: Minutes
Minutes
Highlights: Energy Projects Partnership Manager Beth Landon joined our meeting to talk through her role as main communication link between all…Continue readingCommittee meeting, May 13th 2025
Highlights: Land purchase looking at final details, such as responsibility for boundary fences. CSY are preparing tender documents for the village…Continue readingCommittee meeting, April 8th 2025
Highlights: OCA – Significant progress on winding up OCA to transfer all assets to OCA SCIO. This will be the last…Continue readingOCA/OCA SCIO AGMs, March 4th 2025
Highlights: Brief meeting immediately following the AGMs. The committee voted to retain the existing people in the roles of Chair, Treasurer,…Continue readingCommittee meeting, March 4th 2025
Highlights: Work on the village is currently on hold to some degree, pending progress with the land purchase. OCA members met…Continue readingCommittee meeting, February 5th 2025
Highlights: AGM preparations. Latest village hall cost estimates from the QS are much higher than 2 years ago. Approach from here…Continue readingCommittee meeting, January 15th 2025
Highlights: All current Trustees of the “old” OCA have now signed and agreed, allowing us to wind up OCA and…Continue readingCommittee meeting, November 5th 2024
Highlights: RES gave a presentation to the Committee about the new energy storage facility proposed for a location near Branxton…Continue readingCommittee meeting, April 2nd 2024
Highlights: CSY Architects had provided a series of revised sketches, which took into consideration comments/recommendations made by the ELC Planner.…Continue readingCommittee meeting, March 5th 2024