Lots of sand this week! A large stack of white and orange ton bags are gradually being diminished and the…Continue readingHall Build – Week 23
Author: gareth
Hall Build – Week 22
It’s been a week of heavy digging by hand and by machine for the guys at TRF. The end result…Continue readingHall Build – Week 22
Hall Build – Week 21
The day(s) of the big drill finally arrived! From first thing on Monday, GreenHeat Renewables were on site in force…Continue readingHall Build – Week 21
Hall Build – Week 20
The blocks keep coming… (check out the intricate cuts, joining blocks to steel by TRF!) but this week, we have…Continue readingHall Build – Week 20
Hall Build – Week 19
More blockwork and pipes this week… Three courses of blocks are now all but complete around the main outer wall,…Continue readingHall Build – Week 19
Hall Build – Week 18
A busy week for blockwork! Blocks for the three base courses all around the hall were delivered and largely installed…Continue readingHall Build – Week 18
Hall Build – Week 17
Steelwork done, TRF are back on site and pressing on with the next stages! This week, the central access road…Continue readingHall Build – Week 17
Highlights: The steel frame for the hall is up! OCA are to confirm a couple of aesthetic choices for the…Continue readingCommittee meeting, April 7th 2026
Hall Build – Week 15
Well it’s been very quiet for a few weeks while we waiting for the steel to manufactured but it was…Continue readingHall Build – Week 15
Highlights: SPEN have connected power to the temporary box that will server TRF during the build, but we don’t yet…Continue readingCommittee meeting, March 3rd 2026
