The blocks keep coming… (check out the intricate cuts, joining blocks to steel by TRF!) but this week, we have…Continue readingHall Build – Week 20
Author: gareth
Hall Build – Week 19
More blockwork and pipes this week… Three courses of blocks are now all but complete around the main outer wall,…Continue readingHall Build – Week 19
Hall Build – Week 18
A busy week for blockwork! Blocks for the three base courses all around the hall were delivered and largely installed…Continue readingHall Build – Week 18
Hall Build – Week 17
Steelwork done, TRF are back on site and pressing on with the next stages! This week, the central access road…Continue readingHall Build – Week 17
Hall Build – Week 15
Well it’s been very quiet for a few weeks while we waiting for the steel to manufactured but it was…Continue readingHall Build – Week 15
Highlights: SPEN have connected power to the temporary box that will server TRF during the build, but we don’t yet…Continue readingCommittee meeting, March 3rd 2026
Hall Build – Week 09
Not much has changed on site this week, but that doesn’t mean that TRF have been on holiday! All the…Continue readingHall Build – Week 09
Hall Build – Week 08
It’s been a relatively quiet week. While the concrete of the foundations is now set and level, we have a…Continue readingHall Build – Week 08
Highlights: Original OCA is still hanging on, due to difficulties in the OSCR processes to close it, but we expect…Continue readingOCA and OCA SCIO AGMs, February 8th 2026
Hall Build – Week 07
It’s concrete week! The first week of new things going in, instead of old things and dirt coming out! Two…Continue readingHall Build – Week 07
