We have a full roof covering! The guys from Artisan Roofing have been on site most of the week, and…Continue readingHall Build – Week 47
Author: gareth
Hall Build – Week 46
Big progress on the roof! We now have the whole back elevation complete and almost all of the front. You…Continue readingHall Build – Week 46
Hall Build – Week 45
Well we knew storm Boelo was coming, so TRF battened down everything they could at the end of last week…Continue readingHall Build – Week 45
Hall Build – Week 44
The lights are on! Ok, so they’re temporary lights for TRF to work by indoors, but it does mean we…Continue readingHall Build – Week 44
Hall Build – Week 43
Cracking on with the roof… This week, the rear elevation of the roof has had its last membrane layer added…Continue readingHall Build – Week 43
Hall Build – Week 42
We have one half of a dry hall…! The rear elevation of the roof has now been lined, battened, and…Continue readingHall Build – Week 42
Highlights: The Ridge have advised that they will be putting in a claim to extend costs and build time for…Continue readingCommittee meeting, October 6th 2026
Hall Build – Week 40
It’s been full pace on getting the roof timbers finished this week. TRF have hired in some extra hands to…Continue readingHall Build – Week 40
Hall Build – Week 39
Scaffolding up! All four sides of the main building are now scaffolded, meaning the TRF guys can get on with…Continue readingHall Build – Week 39
Hall Build – Week 38
Work continues on the front half of the roof this week. We now have the timber framing up for the…Continue readingHall Build – Week 38