Digger and dumper back on site this week. Not the great big ones we had at the start to do…Continue readingHall Build – Week 37
Category: News
News
Hall Build – Week 36
It’s raining… better get the roof up. All work this week has been “upstairs” (up scaffold) getting outer walls and…Continue readingHall Build – Week 36
Why not publish locally?
Choose a locally managed website hosting service? Locally grown, no nasties.Continue readingWhy not publish locally?
Update August 2026
We submitted our Community Asset Transfer Request (so called) to NHS Lothian back in January and were originally expecting a…Continue readingUpdate August 2026
Normally on the Second Wed of the month 12.30-14.00 In St. Anne’s Church, Westgate, Dunbar, EH42 1JL Next café, Wednesday…Continue readingClimate Café
Hall Build – Week 35
Busy week for the TRF guys, working on two sections at once. The stone masons have started work rebuilding and…Continue readingHall Build – Week 35
Hall Build – Week 34
It’s flower show week! Of course, that hasn’t stopped progress with the build, but TRF have made some extra efforts…Continue readingHall Build – Week 34
We are delighted to launch a new 2-week pilot all-female Constructing Futures training programme, starting on Monday 7 September 2026.…Continue readingAnnouncing Our New Pilot All-Female Constructing Futures Programme